Job JNW0105 Route VARIOUS VARIOUS County. 19 BRIDGE REHABILITATIONS on various routes in Daviess, Grundy, Harrison, Linn, Mercer, Putnam, and Sullivan Counties, the total length of improvement being 0.347 miles. (2): Job JNW0106 Route VARIOUS VARIOUS County. 12 BRIDGE REHABILITATIONS on various routes in Gentry, Harrison, Nodaway and Worth Counties, the total length of improvement being 0.294 miles.

This is a Missouri Department of Transportation (MoDOT) federal highway construction project comprising two separate bridge rehabilitation jobs (JNW0105 and JNW0106) across seven counties in northern Missouri. The work includes 19 bridge rehabilitations on various routes in Daviess, Grundy, Harrison, Linn, Mercer, Putnam, and Sullivan Counties (Job JNW0105, 0.347 miles) and 12 bridge rehabilitations in Gentry, Harrison, Nodaway, and Worth Counties (Job JNW0106, 0.294 miles). The scope involves cleaning and epoxy coating of bridge structures, concrete protective coatings, surface preparation, re-grouting, joint sealing, roadway items including bituminous pavement, microsurfacing, seal coat, guardrail work, and signing. This is a federal project (FAS S102(90)) subject to Davis-Bacon prevailing wage requirements and DBE participation goals. Source scope cues include: bid bond, bidders must use the MoDOT provided bid bond forms. The project specific bond form is included in the request for bid. The project specific and annual bid bon.

BID WITH CAUTION 11 red flags detected : Electronic Bid Submission Only (Paper Bids Non-Responsive)

Free RFP preview

The quick read before you decide to bid

Bid/no-bid recommendation

BID WITH CAUTION

Scope summary

This is a Missouri Department of Transportation (MoDOT) federal highway construction project comprising two separate bridge rehabilitation jobs (JNW0105 and JNW0106) across seven counties in northern Missouri. The work includes 19 bridge rehabilitations on various routes in Daviess, Grundy, Harrison, Linn, Mercer, Putnam, and Sullivan Counties (Job JNW0105, 0.347 miles) and 12 bridge rehabilitations in Gentry, Harrison, Nodaway, and Worth Counties (Job JNW0106, 0.294 miles). The scope involves cleaning and epoxy coating of bridge structures, concrete protective coatings, surface preparation, re-grouting, joint sealing, roadway items including bituminous pavement, microsurfacing, seal coat, guardrail work, and signing. This is a federal project (FAS S102(90)) subject to Davis-Bacon prevailing wage requirements and DBE participation goals. Source scope cues include: bid bond, bidders must use the MoDOT provided bid bond forms. The project specific bond form is included in the request for bid. The project specific and annual bid bon.

Submission deadline

2026-08-14

Red flag teaser

11 red flags detected including Electronic Bid Submission Only (Paper Bids Non-Responsive).

Locked analysis

Full red flag list with excerpts

11 found

Electronic Bid Submission Only (Paper Bids Non-Responsive)

high

All bids shall be submitted electronically using "Bid Express Secure Internet Bidding" at www.bidx.com. Any paper bid submitted will be considered irregular per section 102.8 of the Missouri Standard Specifications for Highway Construction.

Federal Project Compliance (Davis-Bacon Prevailing Wage)

high

THIS JOB SHALL BE CONSTRUCTED UNDER FEDERAL PROJECT NUMBER(S): FAS S102(90)

Liquidated Damages

high

…pliance With Contract Provisions....................... item (2) Period of Performance..................................... item (3) Liquidated Damages........................................ item (4) Itemized Bid.............................................. item (5) Trainees.................................................. item (6) DBE Certification*........................................ ite

Prequalification Required 7 Days Before Bid Opening

high

Submit completed Contractor Prequalification Questionnaire with attachments not later than seven (7) days prior to the date and hour of the bid opening. See Secs 101-103 of the Missouri Standard Specifications for Highway Construction, and Rule 7 CSR 10-15.010, "Prequalification to Bid of Certain Contractors".

Alternate Pavement Options (Bidding Requirement)

medium

Alternate Pavements; to exercise this option, separate pay items, descriptions and quantities are included in the itemized proposal for each of the two alternates. The bidder shall bid only one of the two alternates and leave the contract unit price column blank for any pay item listed for the other alternate.

Locked analysis

All deadlines table

4 dates
ItemDue
Contractor Prequalification Questionnaire Submission 2026-08-14
Electronic Bid Submission Deadline 2026-08-21
Subcontractor Disclosure Form Submission (if not available at bid time) 2026-08-24
Annual Bid Bond Execution Deadline 2026-06-15

Locked analysis

Required certifications checklist

15 items
  • Complete bid/proposal form
  • Include bid bond
  • Include references or past project experience
  • Verify requirement: Contractor Prequalification
  • Verify requirement: DBE Identification Submittal
  • Verify requirement: Digital ID for Electronic Bid Submission
  • Verify requirement: Federal Project Certifications (Affirmative Action, Disbarment, Anti-Collusion, Lobbying)
  • Verify requirement: Subcontractor Disclosure Form

Locked workspace

Guest view link to the interactive analysis

Open the full workspace to review evidence, generate response documents, and work from the analyzed checklist.

Analyzing your own RFP?

Email any RFP PDF to rfp@mail.bidterms.com and get a full analysis back in under 5 minutes, free.

Or start your free trial →

Related public analyses

More RFPs in a similar lane

View all