Job JNE0024 Route 11 ADAIR, KNOX, LINN, SULLIVAN County. Resurface from Route 15 near Baring to Route 129 in Linn County, the total length of improvement being 41.787 miles. (2): Job JNE0254 Route 6 ADAIR County. Resurface from east of Baltimore Street to west of Route 63 near Kirksville, the total length of improvement being 0.865 miles.

This is a Missouri Department of Transportation (MoDOT) highway resurfacing project consisting of two jobs: Job JNE0024 on Route 11 in Adair, Knox, Linn, and Sullivan Counties (41.787 miles of resurfacing from Route 15 near Baring to Route 129 in Linn County), and Job JNE0254 on Route 6 in Adair County (0.865 miles of resurfacing from east of Baltimore Street to west of Route 63 near Kirksville). The work is funded under Federal Project Numbers FAF 6-3(17) and FAF 6-2(62), making this a federal-aid highway project subject to Davis-Bacon prevailing wage, DBE participation goals, and other federal compliance requirements. The scope includes bituminous pavement resurfacing, coldmilling, tack coat application, pavement markings, temporary traffic control, and mobilization. Source scope cues include: bid bond, bidders must use the MoDOT provided bid bond forms. The project specific bond form is included in the request for bid. The project specific and annual bid bon.

BID WITH CAUTION 9 red flags detected : Federal Funding Compliance (Davis-Bacon / Prevailing Wage)

Free RFP preview

The quick read before you decide to bid

Bid/no-bid recommendation

BID WITH CAUTION

Scope summary

This is a Missouri Department of Transportation (MoDOT) highway resurfacing project consisting of two jobs: Job JNE0024 on Route 11 in Adair, Knox, Linn, and Sullivan Counties (41.787 miles of resurfacing from Route 15 near Baring to Route 129 in Linn County), and Job JNE0254 on Route 6 in Adair County (0.865 miles of resurfacing from east of Baltimore Street to west of Route 63 near Kirksville). The work is funded under Federal Project Numbers FAF 6-3(17) and FAF 6-2(62), making this a federal-aid highway project subject to Davis-Bacon prevailing wage, DBE participation goals, and other federal compliance requirements. The scope includes bituminous pavement resurfacing, coldmilling, tack coat application, pavement markings, temporary traffic control, and mobilization. Source scope cues include: bid bond, bidders must use the MoDOT provided bid bond forms. The project specific bond form is included in the request for bid. The project specific and annual bid bon.

Submission deadline

2026-08-21

Red flag teaser

9 red flags detected including Federal Funding Compliance (Davis-Bacon / Prevailing Wage).

Locked analysis

Full red flag list with excerpts

9 found

Federal Funding Compliance (Davis-Bacon / Prevailing Wage)

high

THIS JOB SHALL BE CONSTRUCTED UNDER FEDERAL PROJECT NUMBER(S): FAF 6-3(17), FAF 6-2(62). By signing and submitting this bid, the bidder makes the certifications appearing in Sec. 102.18.1(regarding affirmative action and equal opportunity), Sec. 102.18.2 (regarding disbarment, eligibility, indictments, convictions, or civil judgments), Sec. 102.18.3 (regarding anti-collusion), and Sec. 102.18.4 (regarding lobbying activities).

Liquidated Damages

high

…pliance With Contract Provisions....................... item (2) Period of Performance..................................... item (3) Liquidated Damages........................................ item (4) Itemized Bid.............................................. item (5) Trainees.................................................. item (6) DBE Certification*........................................ ite

Termination for Misconduct (Fraud, Dishonesty, Misrepresentation)

high

As provided in Sec. 108.13, the Commission may terminate the contract for acts of misconduct, which includes but is not limited to fraud, dishonesty and material misrepresentation or omission of fact within the bid submission.

Bid Bond Required

medium

The bidder shall submit a Bid Guaranty meeting the requirements of Sec 102 of the Missouri Standard Specifications for Highway Construction. If submitting a project specific or annual bid bond, bidders must use the MoDOT provided bid bond forms. The project specific bond form is included in the request for bid. The project specific and annual bid bond forms are also available on MoDOT's website. Annual bid bonds shall be executed by June 15th of each year.

Combination Bid Requirement

medium

If more than one Job Number is listed for this call, then combination bids will be required on the Jobs listed above. Combination bids will be in accordance with Sec 102.12. By selecting "All or None" the bidder desires to combine all projects in accordance with Sec 102.12.2.1.

Locked analysis

All deadlines table

4 dates
ItemDue
Bid Submission Deadline 2026-08-21
Contractor Prequalification Questionnaire Submission 2026-08-14
Subcontractor Disclosure Form (if not submitted with bid) 2026-08-24
Annual Bid Bond Submission Deadline 2026-06-15

Locked analysis

Required certifications checklist

15 items
  • Complete bid/proposal form
  • Include bid bond
  • Include references or past project experience
  • Verify requirement: Anti-Collusion Certification
  • Verify requirement: Contractor Prequalification
  • Verify requirement: DBE Identification Submittal
  • Verify requirement: Digital ID for Electronic Bid Submission
  • Verify requirement: Employment Authorization Certification

Locked workspace

Guest view link to the interactive analysis

Open the full workspace to review evidence, generate response documents, and work from the analyzed checklist.

Analyzing your own RFP?

Email any RFP PDF to rfp@mail.bidterms.com and get a full analysis back in under 5 minutes, free.

Or start your free trial →

Related public analyses

More RFPs in a similar lane

View all