Source scope cues include: CITY OF RIVERSIDE PUBLIC UTILITIES; CITY OF RIVERSIDE CONTRACTOR CUSTOMER; Prevailing Wage/Certified Payrolls. .................................................................. 30 5-4 INSURANCE. ..............; 3-13 COMPLETION, ACCEPTANCE AND WARRANTY.; 2 Prevailing Wage/Certified Payrolls.; 6 Deductibles and Self-Insured Retentions.; 1 Removal and Replacement of Surface Improvements.; Board - The City of Riverside Board of Public Utilities.; RPU - The City of Riverside Public Utilities Department.; communications must be in written format and addressed only to Q&A Tab in Planetbids.; be submitted via the Q&A Tab in Planetbids.; NO HARD COPY OR EMAILED BIDS WILL BE ACCEPTED.; Contractor shall provide proof to City that notifications have been made (i.; the Contractor has obtained the necessary permits.; 3900 Main Street, Riverside CA; 3750 University Avenue; 3900 Main Street, Riverside, which schedule is open for inspection to any interested party on request. The Contractor and all.

BID WITH CAUTION 16 red flags detected : Back-Charge / Setoff Rights

Free RFP preview

The quick read before you decide to bid

Bid/no-bid recommendation

BID WITH CAUTION

Scope summary

Source scope cues include: CITY OF RIVERSIDE PUBLIC UTILITIES; CITY OF RIVERSIDE CONTRACTOR CUSTOMER; Prevailing Wage/Certified Payrolls. .................................................................. 30 5-4 INSURANCE. ..............; 3-13 COMPLETION, ACCEPTANCE AND WARRANTY.; 2 Prevailing Wage/Certified Payrolls.; 6 Deductibles and Self-Insured Retentions.; 1 Removal and Replacement of Surface Improvements.; Board - The City of Riverside Board of Public Utilities.; RPU - The City of Riverside Public Utilities Department.; communications must be in written format and addressed only to Q&A Tab in Planetbids.; be submitted via the Q&A Tab in Planetbids.; NO HARD COPY OR EMAILED BIDS WILL BE ACCEPTED.; Contractor shall provide proof to City that notifications have been made (i.; the Contractor has obtained the necessary permits.; 3900 Main Street, Riverside CA; 3750 University Avenue; 3900 Main Street, Riverside, which schedule is open for inspection to any interested party on request. The Contractor and all.

Submission deadline

2022-06-29

Red flag teaser

16 red flags detected including Back-Charge / Setoff Rights.

Locked analysis

Full red flag list with excerpts

16 found

Back-Charge / Setoff Rights

high

…ges, invoiced fee or other debt which is owed, or which becomes owed, by Contractor to City, City reserves the right to withhold and offset said amounts from any payments, refunds or reimbursements owed by City to Contractor under the Contract. Notice of such withholding and offset shall promptly be given to Contractor by City in writing. In the event of a dispute as to the amount owed or whether

Broad Indemnification

high

…is hereby relieved at all times from any indebtedness or claim other than payments under terms of the Contract. The Contractor will indemnify and hold harmless the City and its officers and employees from any loss, demand, damages, claims or actions arising from or in connection with said indebtedness. 3-2 SELF PERFORMANCE. There are no "Specialty Items" on this project. 3-3.1 Subcontractor Quali

Liquidated Damages

high

6-9 LIQUIDATED DAMAGES ................................................................................... 49 SECTION 7 – MEASUREMENT AND PAYMENT ............................................................... 50 7-1 MEASUREMENT OF QUANTITIES FOR UNIT PRICE WORK .................. 50 7-3 PAYMENT. ......................................................................................................

Mandatory Pre-Bid / Pre-Proposal Meeting

high

…2 1-6.1.1 Scope of Contract Award. .................................................................................. 12 1-6.1.2 Non-Mandatory Pre-Bid Conference ................................................................ 13 1-6.1.3 Examination of Work Site, Proposal Forms, Plans and Specifications. ...... 13 1-6.1.4 Contractor Customer Service Standards. ....................................

No Material Substitutions Without Owner Approval

high

…boxes shall be used. 212-10.6.3 Terminal Housing Boxes. Meter boxes shall be provided for test lead terminal housing and water quality sampling station. The size shall be the same as for a 3/4-inch meter to 1-inch meter. 212-10.6.4 Approved Manufacturers and Models. Any substitution must be approved by the Engineer and shall be of the same size and description as those specified in Appendix II. 7

Locked analysis

All deadlines table

6 dates
ItemDue
Notice Inviting Bids Released 2022-06-29
Non-Mandatory Pre-Bid Meeting 2022-07-05
Final Questions Due 2022-07-11
Responses to Questions Released 2022-07-13
Bids Due 2022-07-19
Tentative Board of Public Utilities Meeting to 2022-08-22

Locked analysis

Required certifications checklist

27 items
  • Include bid bond
  • Include performance bond
  • Include payment bond
  • Attach certificate of insurance
  • Verify general liability insurance limits
  • Verify workers compensation coverage
  • Include contractor license information
  • Acknowledge all addenda

Locked workspace

Guest view link to the interactive analysis

Open the full workspace to review evidence, generate response documents, and work from the analyzed checklist.

Analyzing your own RFP?

Email any RFP PDF to rfp@mail.bidterms.com and get a full analysis back in under 5 minutes, free.

Or start your free trial →

Related public analyses

More RFPs in a similar lane

View all