JESUS S. DURAN EASTSIDE LIBRARY CONSTRUCTION PROJECT

Source scope cues include: City of Riverside; City of Riverside Building and; acting within the scope of their particular duties.; associated with site work, utilities and parking reconfiguration.; Riverside Building Department for the structure located at 2060 University Avenue, Riverside 92507.; NO HARD COPY BIDS WILL BE ACCEPTED.; telephone number of an agent located in the State of California who is authorized to act for the bonding company.; 1) Permits from other agencies as may be required by law.; architect, proper agency or department in order to obtain approval and/or proper permits.; cost, permits and insurance required of the Contractor by other agencies and organizations.; or other forces, from the supplier thereof as evidenced by supplier's invoice.; 2060 UNIVERSITY AVENUE, RIVERSIDE CA; 2060 University Avenue, Riverside, CA; 3900 Main Street; Electrical Contractor; Plumbing Contractor.

BID WITH CAUTION 15 red flags detected : Back-Charge / Setoff Rights

Free RFP preview

The quick read before you decide to bid

Bid/no-bid recommendation

BID WITH CAUTION

Scope summary

Source scope cues include: City of Riverside; City of Riverside Building and; acting within the scope of their particular duties.; associated with site work, utilities and parking reconfiguration.; Riverside Building Department for the structure located at 2060 University Avenue, Riverside 92507.; NO HARD COPY BIDS WILL BE ACCEPTED.; telephone number of an agent located in the State of California who is authorized to act for the bonding company.; 1) Permits from other agencies as may be required by law.; architect, proper agency or department in order to obtain approval and/or proper permits.; cost, permits and insurance required of the Contractor by other agencies and organizations.; or other forces, from the supplier thereof as evidenced by supplier's invoice.; 2060 UNIVERSITY AVENUE, RIVERSIDE CA; 2060 University Avenue, Riverside, CA; 3900 Main Street; Electrical Contractor; Plumbing Contractor.

Submission deadline

2025-04-02

Red flag teaser

15 red flags detected including Back-Charge / Setoff Rights.

Locked analysis

Full red flag list with excerpts

15 found

Back-Charge / Setoff Rights

high

…ges, invoiced fee or other debt which is owed, or which becomes owed, by Contractor to City, City reserves the right to withhold and offset said amounts from any payments, refunds or reimbursements owed by City to Contractor under the Contract. Notice of such withholding and offset shall promptly be given to Contractor by City in writing. In the event of a dispute as to the amount owed or whether

Broad Indemnification

high

…is hereby relieved at all times from any indebtedness or claim other than payments under terms of the Contract. The Contractor will indemnify and hold harmless the City and its officers and employees from any loss, demand, damages, claims or actions arising from or in connection with said indebtedness. 2-3 SUBCONTRACTS 2-3.2 Self Performance. The Contractor shall perform, with its own organizatio

Hazardous Material / Abatement Coordination

high

…tion. Employer’s Liability shall be not less than one million dollars ($1,000,000). d. Contractors’ Pollution Legal Liability and/or Asbestos Legal Liability and/or Errors and Omissions with limits no less than $1,000,000 per occurrence or claim, and $2,000,000 policy aggregate. e. Builders Risk. Currently checking with Risk Management f. No Limitation on Indemnification. These minimum amounts of

Liquidated Damages

high

…ring the Project back on schedule within a reasonable period of time following such request will subject Contractor to assessment of liquidated damages at the daily rate specified for late completion. The Contractor shall not shorten or delete specified cure times or omit portions of the Work in order to bring the Project back within schedule unless such measures are mutually agreed to by the Pro

Prevailing Wage / Certified Payroll

high

…patronage in the City, Contractor shall use its best efforts to purchase supplies within the City limits. 7-2.2 Laws. A schedule of prevailing wage rates as published by the California Department of Industrial Relations for the types of work to be done under these Special Provisions is on file in the office of the City Clerk, City Hall, 3900 Main Street, Riverside, which schedule is open for insp

Locked analysis

All deadlines table

5 dates
ItemDue
BIDS DUE 2025-04-02
Request for Bids Released 2025-02-26
Non-Mandatory Pre-Bid Job Walk 2025-03-11
Final Questions Due 2025-03-18
Responses to Questions Released 2025-03-25

Locked analysis

Required certifications checklist

26 items
  • Complete bid/proposal form
  • Include bid bond
  • Include performance bond
  • Include payment bond
  • Attach certificate of insurance
  • Verify general liability insurance limits
  • Verify workers compensation coverage
  • Include contractor license information

Locked workspace

Guest view link to the interactive analysis

Open the full workspace to review evidence, generate response documents, and work from the analyzed checklist.

Analyzing your own RFP?

Email any RFP PDF to rfp@mail.bidterms.com and get a full analysis back in under 5 minutes, free.

Or start your free trial →

Related public analyses

More RFPs in a similar lane

View all