HD-S2537 Phase II Harbor Plaza Facilities Site Improvements at Harbor Plaza Drive, Pier G

Source scope cues include: City of Long Beach; City of Long Beach Construction; Protect existing utilities and pipelines, as shown on the Drawings.; The Work Site is located in front of Harbor Department Maintenance Facilities.; culverts, curbs, gutters, underdrains, etc.; inspections and notifications required by permits.; Define arrangements for safety, first aid, emergency actions and security.; Discuss coordination and notification for utility work, and use of onsite utilities.; everything on or after the data date is work planned to be completed.; number, Data Date, Primavera XER file, and date of the submittal on each page.; data to explain the basis of the shorter time for performance.; Activity descriptions shall briefly convey scope and location of work indicated.; weather sensitive activities, submittals, and permits throughout the duration of the project.; 1 certified street; 12328 Hibiscus Road; 2801 Madera Road; Electrical Contractors; electrical contractor.

BID WITH CAUTION 8 red flags detected : Guaranteed Maximum Price (GMP) / Hard Budget Cap

Free RFP preview

The quick read before you decide to bid

Bid/no-bid recommendation

BID WITH CAUTION

Scope summary

Source scope cues include: City of Long Beach; City of Long Beach Construction; Protect existing utilities and pipelines, as shown on the Drawings.; The Work Site is located in front of Harbor Department Maintenance Facilities.; culverts, curbs, gutters, underdrains, etc.; inspections and notifications required by permits.; Define arrangements for safety, first aid, emergency actions and security.; Discuss coordination and notification for utility work, and use of onsite utilities.; everything on or after the data date is work planned to be completed.; number, Data Date, Primavera XER file, and date of the submittal on each page.; data to explain the basis of the shorter time for performance.; Activity descriptions shall briefly convey scope and location of work indicated.; weather sensitive activities, submittals, and permits throughout the duration of the project.; 1 certified street; 12328 Hibiscus Road; 2801 Madera Road; Electrical Contractors; electrical contractor.

Submission deadline

Not listed in the public preview.

Red flag teaser

8 red flags detected including Guaranteed Maximum Price (GMP) / Hard Budget Cap.

Locked analysis

Full red flag list with excerpts

8 found

Guaranteed Maximum Price (GMP) / Hard Budget Cap

high

…ent for the SCE Work Order shown on SCE Plan No. 661557_0.01 included in Appendix HH shall be reimbursed by the City as an Allowance not to exceed $25,000 as stated in the Schedule of Bid Items. B. No separate measurement and payment will be made for any other Work covered by this Section. The cost of this Work shall be considered incidental to and included in the prices for other items provided

Hazardous Material / Abatement Coordination

high

…02 RELATED WORK SPECIFIED ELSEWHERE Refer to the following Specification Sections for additional requirements: 1. Section 02 82 13, “Asbestos Abatement” 2. Section 31 00 00, “Earthwork” 3. Section 01 76 00, “Protecting Installed Construction” 4. Section 31 23 33, “Trenching and Backfilling” 5. Section 5: Utilities, Standard Specifications for Public Works Construction (The GreenBook) 1.03 SUBMITT

Liquidated Damages

high

…ablishes the period and duration in which the City expects the work to be performed (see Special Conditions “Time for Completion and Liquidated Damages”). Any schedule that shows completion ahead of the Contract time shall include additional supporting data to explain the basis of the shorter time for performance. The City may (1) notify the Contractor that the Contract time is being adjusted by

No Material Substitutions Without Owner Approval

high

…disfigurements. 1. Plant names shall conform to the "Sunset, Western Garden Book" latest edition. 2. Tag one plant of each variety for identifying purposes. 3. Plants shall be inspected and approved prior to planting by the Engineer. 4. When plants of a specified kind or size are not available, substitution may be made upon approval of the Engineer. HD-S2537 TS-250 Planting Div. 32, Sect. 32 90 0

Differing / Unknown Site Conditions (Contractor Risk)

medium

…each, California, as shown on the Drawings. 2. Laydown area: As shown on the Drawings. 3. Crusher site: As shown on the Drawings. B. EXISTING SITE CONDITIONS 1. The Work Site is located in front of Harbor Department Maintenance Facilities. One third of the area is paved to accommodate Middle Harbor Development Construction Trailer, Survey Division Trailer, and parking lot servicing the trailers.

Locked analysis

All deadlines table

0 dates
ItemDue
No deadlines detected.

Locked analysis

Required certifications checklist

6 items
  • Attach certificate of insurance
  • Acknowledge all addenda
  • Confirm mandatory pre-bid meeting or site visit attendance
  • Include references or past project experience
  • Include safety documents if required
  • Verify requirement: Commercial General Liability Insurance

Locked workspace

Guest view link to the interactive analysis

Open the full workspace to review evidence, generate response documents, and work from the analyzed checklist.

Analyzing your own RFP?

Email any RFP PDF to rfp@mail.bidterms.com and get a full analysis back in under 5 minutes, free.

Or start your free trial →

Related public analyses

More RFPs in a similar lane

View all