Liquidated Damages
high…period and duration in which the City expects the work to be performed (see SC-6 “Contract Time” for duration and SC-6.3 “Amount of Liquidated Damages”). Any schedule that shows completion ahead of the Contract time shall include additional supporting data to explain the basis of the shorter time for performance. The City may (1) notify the Contractor that the Contract time is being adjusted by C