Del Rio Sewer Force Main Rehabilitation

Source scope cues include: CITY OF SACRAMENTO SPECIAL PROVISIONS; City of Sacramento; 06 Proof of Compliance with Contract .; 28 Fiberglass Reinforced Polymer Mortar Pipe .; in-place-pipe lining (CIPP) and replacement of an existing blowoff.; Traffic control as needed to complete the rehabilitation and replacement work.; documents or other satisfactory proofs as to his compliance with such requirements.; 72-inch force main in the vicinity of the new blowoff prior to blowoff replacement.; Use the accepted schedule that has a data date closest to and before the event.; temporary discharge permits required to complete the Work.; replacement of the monument or marker.; located in Appendices: A, B, C, D, E, F, G, and H for more information.; at the N11 valve structure, rehabilitation work, and blowoff replacement.; This data is being provided for informational purposes only.; repair, inspection, and maintenance of the system.; Contractor prior to the blowoff replacement.; replacement dewatering water into the 114-inch combined sewer at MH510.; comprehensive coverage of surface features, utilities, and adjacent structures..

BID WITH CAUTION 7 red flags detected : Broad Indemnification

Free RFP preview

The quick read before you decide to bid

Bid/no-bid recommendation

BID WITH CAUTION

Scope summary

Source scope cues include: CITY OF SACRAMENTO SPECIAL PROVISIONS; City of Sacramento; 06 Proof of Compliance with Contract .; 28 Fiberglass Reinforced Polymer Mortar Pipe .; in-place-pipe lining (CIPP) and replacement of an existing blowoff.; Traffic control as needed to complete the rehabilitation and replacement work.; documents or other satisfactory proofs as to his compliance with such requirements.; 72-inch force main in the vicinity of the new blowoff prior to blowoff replacement.; Use the accepted schedule that has a data date closest to and before the event.; temporary discharge permits required to complete the Work.; replacement of the monument or marker.; located in Appendices: A, B, C, D, E, F, G, and H for more information.; at the N11 valve structure, rehabilitation work, and blowoff replacement.; This data is being provided for informational purposes only.; repair, inspection, and maintenance of the system.; Contractor prior to the blowoff replacement.; replacement dewatering water into the 114-inch combined sewer at MH510.; comprehensive coverage of surface features, utilities, and adjacent structures..

Submission deadline

Not listed in the public preview.

Red flag teaser

7 red flags detected including Broad Indemnification.

Locked analysis

Full red flag list with excerpts

7 found

Broad Indemnification

high

operations. The Contractor shall be responsible for any violations of laws, regulations or permits and shall indemnify and hold the City harmless from any and all damages, including but not limited to fines, penalties and lawsuits which arise from such violations. 2.06 Work Performed by City Crews The Contractor is advised that City crews will operate Sump 2 in order to perform the system shut dow

Differing / Unknown Site Conditions (Contractor Risk)

medium

…......21 2.06 Work Performed by City Crews ..................................................................................28 2.07 Existing Site Conditions .............................................................................................28 2.08 Handling and Removal of Hazardous or Contaminated Materials ...........................28 2.09 Health and Safety ...........................

Extended Warranty (> 1 Year)

medium

…clean surfaces and remove debris. Restore disturbed surfaces to original or improved conditions. E. Warranty 1. Provide a minimum of 2-year warranty covering materials and workmanship, including gate operation and finish. 3.12 Tree Removal, Pruning, Preservation and Protection Requirements The objective of this Section is to reduce the negative impacts of construction on trees. Tree protection me

Occupied Building Constraints

medium

…patible contact Engineer and coating manufacturer for recommendations. 3. Existing interior finished spaces: where existing interior occupied spaces are scheduled to be coated, perform surface preparation and cleaning without damage to existing finishes, electronics, and equipment that cannot be removed prior to coating. Surface preparation and cleaning shall include the following steps until eff

Section 3 / Community / Local Hiring Requirement

medium

…rams (for piping equal to and greater than 8-inches in diameter), bulkhead information, and pipe closure information as specified in Section 3.27 Buried Pipe Installation. 3. Affidavit of Compliance: Furnish a certified affidavit of compliance from the pipe manufacturer guaranteeing that the pipe and other products or materials furnished hereunder are in compliance with the requirements of the St

Locked analysis

All deadlines table

0 dates
ItemDue
No deadlines detected.

Locked analysis

Required certifications checklist

5 items
  • Include contractor license information
  • Acknowledge all addenda
  • Include references or past project experience
  • Include safety documents if required
  • Verify requirement: Contractor and Subcontractor Licenses

Locked workspace

Guest view link to the interactive analysis

Open the full workspace to review evidence, generate response documents, and work from the analyzed checklist.

Analyzing your own RFP?

Email any RFP PDF to rfp@mail.bidterms.com and get a full analysis back in under 5 minutes, free.

Or start your free trial →

Related public analyses

More RFPs in a similar lane

View all