Pay-If-Paid Clause
critical…ity to incorporate all necessary activities to cover the entire Work scope. 12. A favorably reviewed Baseline Progress Schedule is a condition precedent to payment. B. Cost Loading 1. Work activities other than third-party and District-managed activities shall be cost loaded. No activity shall have a value greater than $50,000 except for activities representing major Equipment purchases or instal